• LATEST NEWS
  • INDIA
  • WORLD
  • ENTERTAINMENT
  • LIFESTYLE
  • BUSINESS
  • EDUCATION
  • CRICKET
  • TECH
  • SPORTS
  • AUTO
  • SPIRITUAL
  • Fashion
  • HOROSCOPE
  • PHOTO STORIES
  • WEATHER
  • CALCULATORS
  • BRANDVERSE
  • FLASH
  • Videos
  • Cric Daily
  • Astro Daily
  • Flash
  • Search
  • In Focus
  • Jamui Assault Case
  • IIT Bombay Suicide Case
  • Iran-US War
  • Asian Games Medals Tally
  • AI Bootcamp
  • Mutual Funds Mastery
  • Opinion
  • Smart Guide
  • Jagran Reviews
  • Home
  • Uttar Pradesh

Ghaziabad PMAY Scheme: A 6-Year Wait For Homes, Allottees' Hopes Fade Amidst Delays

Beneficiaries awaiting homes in Ghaziabad under the Pradhan Mantri Awas Yojana have been left disappointed. Despite a draw being held six years ago, many have been unable to take possession of their properties due to official negligence. The Ghaziabad Development Authority is now attempting to complete unfinished development work, but the scheme remains mired in controversy.

Author: Akansha Pandey
Fri, 03 Oct 2025 12:48 PM (IST)
Source:Jagran News Network
Ghaziabad PMAY Scheme: A 6-Year Wait For Homes, Allottees' Hopes Fade Amidst Delays
People waiting to receive a house under the Pradhan Mantri Awas Yojana have so far been met with disappointment.

Six years after receiving allotment letters in a 2019 draw, beneficiaries of the Pradhan Mantri Awas Yojana (PMAY) in Ghaziabad are still waiting to get possession of their homes. The ambitious central government scheme, launched seven years ago to provide housing for the lower-income group, has been stalled by official negligence, causing the hopes of allottees to fade.

Multiple Projects Delayed Beyond Deadlines

The Ghaziabad Development Authority launched several projects under the PMAY (Urban) scheme with a promised two-year completion timeline. These include:

Madhuban Bapudham: (856 homes) Launched on July 11, 2018, with a target completion of 2020.

Dasna: Launched on March 11, 2019.

Niwari: Launched on June 10, 2019.

Noor Nagar: Launched on December 20, 2019.

Pratap Vihar: Launched in 2022.

Despite a lottery draw being held in 2019 to allocate the flats, none of the beneficiaries have received possession.

External Development Work Remains Incomplete

The primary reason for the delay is the failure to complete essential external development work. The Jal Nigam (Water Corporation) was responsible for critical infrastructure, including the connection of external water pipelines and the construction of water head tanks.

Also Read: Gurugram's Golf Course Extension Road Traffic: GMDA Mulls Rs 578 Cr Flyover Or Rs 658 Cr Underpass; Final Decision Rests With CM

According to reports, despite several orders and directives, this work remains unfinished. These failures have brought the Prime Minister's ambitious housing project to a standstill in the city, leaving the intended low-income beneficiaries deprived of their promised homes even after years of waiting.

Also Read: Noida International Airport Wildlife Rescue Centre Set For February 2026 Opening

Join our WhatsApp Channel
Copyright © 2026 Jagran Prakashan Limited.All rights reserved.
For any feedback or complaint,
email to compliant_gro@jagrannewmedia.com
This website uses cookie or similar technologies, to enhance your browsing experience and provide personalised recommendations. By continuing to use our website, you agree to our Privacy Policy and Cookie Policy.