• LATEST NEWS
  • INDIA
  • WORLD
  • ENTERTAINMENT
  • LIFESTYLE
  • BUSINESS
  • EDUCATION
  • CRICKET
  • TECH
  • SPORTS
  • AUTO
  • SPIRITUAL
  • Fashion
  • HOROSCOPE
  • PHOTO STORIES
  • WEATHER
  • CALCULATORS
  • BRANDVERSE
  • FLASH
  • Videos
  • Cric Daily
  • Astro Daily
  • Flash
  • Search
  • In Focus
  • BRICS Summit LIVE
  • iPhone Duo
  • Haiwaan Review
  • 80s AI Photo Trend
  • AI Bootcamp
  • Opinion
  • Smart Guide
  • Jagran Reviews
  • Home
  • Uttar Pradesh

Noida’s 5.5 Km Chilla Elevated Road Work Gains Pace; Early Opening Likely

The construction of the Chilla elevated road is advancing swiftly, promising to alleviate traffic congestion from the Delhi-Noida border to the Mahamaya flyover. Expected to be completed on schedule, the project will enhance connectivity between Noida and Delhi, ensure smoother traffic, and help boost the region's economic growth.

Author: Kamakshi Bishnoi
Mon, 08 Dec 2025 11:09 AM (IST)
Source:Jagran News Network
Noida’s 5.5 Km Chilla Elevated Road Work Gains Pace; Early Opening Likely
Construction work on the Chilla Elevated Road is underway near Sector 14A. (Image: Jagran)

To reduce traffic congestion from the Delhi-Noida border to Mahamaya Flyover, the Noida Authority is constructing a 5.5-kilometre-long, six-lane Chilla elevated road along the Shahdara Drain from the Chilla Regulator. The construction has now gained momentum, and it is expected that vehicles may be able to travel at speed on the elevated road before the set deadline of December 2027.

This construction will provide direct connectivity from the Chilla Elevated Road via the Mayur Vihar Flyover to the Mahamaya Flyover, directly connecting vehicles coming from Mayur Vihar and East Delhi to the Noida-Greater Noida Expressway.

ALSO READ: Goa Nightclub Fire: DJ Moments Away From Performing At Birch By Romeo Lane Escapes Fire, Says She Is 'Shaken'

The project will also benefit travellers heading towards the Yamuna Expressway and Lucknow, along with easing travel to and from the upcoming Noida International Airport in Jewar.

The Chilla Elevated Road, connecting Delhi and Noida, is being constructed for Rs 892 crore. The construction is being carried out by the Uttar Pradesh State Bridge Corporation, while the monitoring and expenditure are being managed by the Noida Authority. The cabinet had approved the government's 50 per cent share of the construction cost on June 6, 2023. The elevated road will be constructed at Rs 787 crore.

A percentage-based charge for the construction will be paid to the Uttar Pradesh Bridge Corporation. Half of this amount will be provided by the UP government, while the remaining half will be borne by the Authority.

The Chilla Elevated Road project dates back to before 2017. Chief Minister Yogi Adityanath laid its foundation stone on January 25, 2019, with the construction beginning in June 2020. The initial estimated cost of the project was Rs 650 crore.

Subsequently, work was halted in November 2021 because the 50 per cent share from the government, as per the agreement, was not received. The Authority had also invested around Rs 70 crore to start the work.

ALSO READ: IndiGo Flight Cancellations Live Updates: Over 300 Flights Axed As Operational Woes Hit Day Seven; Delhi Airport Issues Advisory

After this, the project received cabinet approval in June 2023. Following two tender processes, the Bridge Corporation selected an agency in the second tender, and work commenced in March.

The new, approved design for the Chilla Elevated Road has now been submitted to the Authority. The six-lane road will be built on 269 pillars, with 35 per cent of the pillar piling and capping work completed. Six ramps will be constructed for vehicles to enter and exit.

Chilla Elevated Road Construction Status:

Social Class

Total No.

Completed

Remaining

Pile

1468

1061

407

Pile Cap

269

110

159

Pillar Construction Status:

Construction Complete: 25

Under Construction: 50

“This project will enhance connectivity between Delhi-NCR, the Yamuna Expressway, and the Noida International Airport by linking Mayur Vihar, Sector 14, and Sector 94 to the Noida-Greater Noida Expressway. The estimated cost of the project is around Rs 892 crore, and it is targeted for completion by December 2027. However, the pace is quick, and 35 per cent of the work has already been completed. Vehicles might be able to use the road ahead of schedule,” said Vijay Kumar Rawal, Deputy General Manager (Civil), Noida Authority.

Join our WhatsApp Channel
Copyright © 2026 Jagran Prakashan Limited.All rights reserved.
For any feedback or complaint,
email to compliant_gro@jagrannewmedia.com
This website uses cookie or similar technologies, to enhance your browsing experience and provide personalised recommendations. By continuing to use our website, you agree to our Privacy Policy and Cookie Policy.