Mumbai-Ahmedabad Bullet Train: The Mumbai-Ahmedabad Bullet Train project, being developed by the National High Speed Rail Corporation Limited (NHSRCL), is set to transform the economic landscape of Ahmedabad and the entire corridor by seamlessly connecting major cities into one unified economic powerhouse. This high-speed rail initiative is not just about faster travel—it is a catalyst for growth, investment, and regional development. Pictures of an under-construction bullet train railway station emerged on social media, showing the grandeur of the project.
The Mumbai-Ahmedabad bullet train project is reshaping India’s transport landscape with state-of-the-art stations designed for speed, comfort, and sustainability. These pictures display modern architecture, regionally inspired aesthetics, solar power, and rainwater harvesting. These stations will offer passengers a world-class and environmentally conscious travel experience.
PHOTO | The Mumbai-Ahmedabad bullet train project is reshaping India’s transport landscape with state-of-the-art stations designed for speed, comfort, and sustainability. Featuring modern architecture, regionally inspired aesthetics, solar power, rainwater harvesting, and… pic.twitter.com/IvRlr36l9g
— Press Trust of India (@PTI_News) August 27, 2025
Sharing with you all, 1st glimpse of graphical representation of Surat's Bullet Train station.
— Darshana Jardosh (@DarshanaJardosh) February 10, 2022
The state-of-the-art multi-level station will have external facade and interiors of the station resemble a sparkling diamond - the pride of Surat city. #NayeBharatKiNayiRail #Surat pic.twitter.com/YQppvzEF8Z
The Mumbai-Ahmedabad High Speed Rail (MAHSR) Project, having a length of 508 km is under execution with technical and financial assistance from Government of Japan. Total estimated cost of MAHSR project is approximately Rs.1,08,000 crores. Cumulative Financial expenditure of Rs. 78,839/- crore has been incurred on the project till 30.06.2025.
Here Are The Key updates On The India's Ambitious Infra Project:
* The Bullet train project’s work of the under-sea tunnel (21 Km approximately) featuring a 7 Km under sea passage has started. Out of 4.8 km between Ghansoli and Shilphata in Maharashtra, 4 km stretch is completed.
ALSO READ: What Impact Will 50% US Tariff Have On India's GDP Growth?
Surat bullet train station work progress update. Deadline - August 2026. In 12 months trial runs to start from here. pic.twitter.com/oyIgb7JhWQ
— Indian Infra (@IndiaInfra02) August 15, 2025
* Total 127 kms of viaducts have been handed over to track contractor. Rail laying and erection of Overhead Equipment (OHE) masts commenced. Work of the only tunnel in Gujarat has been completed.
* The Gujarat portion of the corridor between Vapi and Sabarmati is planned to be completed by Dec, 2027. The entire project (BKC to Sabarmati section) is expected to be completed by Dec, 2029.