- By Nidhi Giri
- Thu, 03 Apr 2025 06:48 PM (IST)
- Source:JND
Mumbai-Goa National Highway: The Union Government on Thursday informed the Lok Sabha that the Mumbai-Goa National Highway (NH) – 66 will be completed by September 2025. Union Minister for Road Transport and Highways Nitin Gadkari said the project was affected due to delays in land acquisition and other pre-construction activities as well as cash flow issues with some of the contractors. However, he mentioned that all pending issues have been substantially resolved in close co-ordination with the state government and the balance works are under implementation.
He detailed that the construction of flyovers at Lanja and Pali got delayed due to land acquisition issues while the work of Chiplun Flyover was delayed due to collapse of one span.
“The land acquisition issues for flyovers at Lanja and Pali have been resolved while the design of the Chiplun flyover was reviewed after the above incident. The construction of all the three flyovers is under implementation with completion in phased manner by September 2025”, he said.
Similarly, he said the Shastripul-Bahwandi-Sangameshwar-Nivli road, part of the Aravali to Talekante section of NH-66, was delayed due to delays in land acquisition and other pre-construction activities, as well as the contractor’s cash flow issues.
He said that work in 30.68km out of the total 39.24km is over and the remaining will be completed in a phased manner by September 2025.