In a bid to accelerate major infrastructural projects, Maharashtra Chief Minister Devendra Fadnavis has set deadlines for major metro projects in the state, including Mumbai’s Metro Line 2B (DN Nagar to Mandale) and Pune’s Metro Line 3 (Maan-Hinjewadi-Shivajinagar). During a review meeting held at Sahyadri Guest House, Fadnavis emphasised the need for the timely completion of these projects using advanced technologies and efficient planning.

The deadline for Mumbai’s Metro Line 2B is March 31, 2027, while the deadline for the Pune Metro is March 31, 2026, as quoted by Pune Pulse. 

ALSO READ: Pune Land Deal Scam: Parth Pawar's Firm Must Pay Double Stamp Duty To Cancel Sale Deed

Mumbai Metro Line 2B

- The Mumbai Metro Line 2B will serve stations at Mandalay, Mankhurd, BSNL, Shivaji Chowk, and Diamond Garden. 

- Once completed, the metro line will connect V.N. Purav Marg and the Shiv-Panvel Highway, with plans to link the Harbour Railway Line at Mankhurd and Metro 8A at Mandalay.

- The line is 23.6 km long and is fully elevated. The line is solely developed by the Mumbai Metropolitan Region Development Authority (MMRDA).

Station List

  • ESIC Nagar

  • Prem Nagar

  • Indira Nagar

  • Nanavati Hospital

  • Khira Nagar

  • Saraswat Nagar

  • National College

  • Bandra Metro

  • Income Tax office (ITO)

  • ILFS

  • MTNL Metro

  • SG Barve Marg

  • Kurla(E)

  • Eastern Express Highway (EEH)

  • Chembur

  • Diamond Garden

  • Shivaji Chowk

  • BSNL Metro

  • Mankhurd

  • Mandale Metro

ALSO READ: Nagpur-Goa Shaktipeeth Expressway To Cut Travel Time To 8 Hours, Link 21 Religious Sites | Check Route, Cost, Other Details

Pune Metro Line 3

- The Pune Metro Line-3 is a 23 km fully elevated metro rail line connecting the IT hub of Hinjewadi to Shivajinagar. 

- It was originally scheduled for completion in March 2025, but due to operational roadblocks, the date has been pushed to next year in 2026.

- This public-private partnership project is being developed by a consortium of Tata Group’s TRIL Urban Transport Private Limited (TUTPL) and Siemens Project Ventures. Construction began in November 2021, with the first metro pillar constructed in April 2022.

Station List 

  • Megapolis Circle

  • Embassy Quadron Business Park

  • Dohler

  • Infosys Phase II

  • Wipro Phase II

  • Pall India

  • Shivaji Chowk (Hinjewadi)

  • Hinjewadi

  • Wakad Chowk

  • Balewadi Stadium

  • NICMAR

  • Ram Nagar

  • Laxmi Nagar

  • Balewadi Phata

  • Baner Gaon

  • Baner

  • Krushi Anusadhan (Indian Agricultural Research Institute)

  • Sakal Nagar

  • University (Savitribai Phule Pune University)

  • R.B.I. (Reserve Bank of India)

  • Agriculture College

  • Shivaji Nagar

  • Civil Court