Mumbai Pune Expressway Update: Maharashtra Deputy Chief Minister Eknath Shinde on Monday informed that 95 per cent work on the missing link project on the Mumbai–Pune expressway is complete and in its final stage. The Maharashtra State Road Development Corporation (MSRDC) has said that the stretch will reduce the travel time between Mumbai and Pune by 30 minutes.

As per an Indian Express report, the government sources said that it aims to meet the new deadline of August 2025 for this project. The project is being built at an estimated cost of Rs 6,600 crore. The project has missed deadlines several times before.

READ MORE: Jharkhand Weather Update: Rain, Thunderstorm In Ranchi And 15 Other Districts Today; Strong Winds To Hit Parts

Details Of Project

'Missing Link' is a 5.7 km straight stretch, passing through tunnels and viaducts, that would connect the Khopoli exit and Sinhgad Institute, the two points on the Mumbai-Pune Expressway.

Currently, the e-way is the only route between these two points that passes through the twists and turns of Khandala and Lonavala. Via the e-way, the distance between both points is 19.8 km as of now.

The cost of the project is Rs 6,600 crore, and it will show some intriguing construction marvels like a viaduct of 840 metres and a tunnel of 1.75 km.

READ MORE: Hyderabad To See Week-Long Showers; Yellow Alert For Thunderstorms In Multiple Telangana Districts | IMD Forecast

Among other components are, 650-metre cable-stayed bridge that is 180 metres above the Khandala Valley and an 8.9 km tunnel, part of which runs below Lonavala Lake. The 23.30 metre-wide tunnels are Asia's widest and will feature four lanes and an emergency lane

The project started in March 2019 and was scheduled to be completed by March 2024. However, it was initially delayed to January 2025 and then to March 2025 before the latest push till September 2025.